Elanza

by PRAVIN Viram SATRA

CTS NO. 7624 76241 TO 156, Andheri, 400055

Mar 2019
Possession
90.9%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2017, now proposed Mar 2019 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 90.9%.
MaladMid-income

Retail-and-BPO hub with dense mid-income housing on both sides.

Growth drivers:
Mindspace offices, Link Road retail, Metro 2A.
Who buys here:
Mid-income families, first-time buyers.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800007425
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019originally December 2017
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of Elanza โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Elanza. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.