Under construction

SRUSHTIRAJ TOWER

by CHINNAIAH VENKATESH GOWDA

103/507/14, Tilak Nagar, 400089

Dec 2026
Possession
65.5%
Built
21
Complaints
125
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
  • 21 RERA complaints. 21 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800009157
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2022
Construction
65.5% complete
Units sold
93 of 125

RERA complaint record21 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements15%
Electrical meter room, sub-station, receiving station15%

Building & registration

RERA registered
Aug 2017
Floors
17
Unit mix
125 res ยท 0 comm
Architect
Iqbal Singh

Buyer community

Connect with other buyers and owners of SRUSHTIRAJ TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SRUSHTIRAJ TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.