Ankur Palace

by OSHO Developers

719/8, Borivali, 400092

Feb 2021
Possession
70.5%
Built
2
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Aug 2019, now proposed Feb 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Feb 2021) has passed with construction at 70.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2021 per the RERA filing.
Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800010439
Status
Ongoing
Stage
Certificate Signed
Possession
February 2021originally August 2019
Construction
70.5% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Bore Welldone

Building & registration

RERA registered
Aug 2017
Floors
19

Buyer community

Connect with other buyers and owners of Ankur Palace โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Ankur Palace. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.