Under construction

Bhagwati Ashish

by Pritesh Damji Savla

12, Andheri, 400060

May 2024
Possession
88.6%
Built
4
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Nov 2020, now proposed May 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (May 2024) has passed with construction at 88.6%.
Andheri East / MarolMid-income

Office corridors (SEEPZ, MIDC) with value housing pockets between them.

Growth drivers:
Airport proximity, Metro 1/7, IT-park employment.
Who buys here:
Working couples prioritising commute over frills.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800010515
Status
Ongoing
Stage
Certificate Signed
Possession
May 2024originally November 2020
Construction
88.6% complete
Units sold
0 of 0

RERA complaint record4 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of Bhagwati Ashish โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Bhagwati Ashish. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.