PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

JAI SHREERAM PRASANNA CHSL

by RIYAZ RAMZAN SHAH

CTS 939, 939 / 1 TO 4, Kurla, 400070

Aug 2026
Possession
72.6%
Built
1
Complaints
26
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2022, now proposed Aug 2026 per the RERA filing.
Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800011427
Status
Ongoing
Stage
Certificate Signed
Possession
August 2026originally June 2022
Construction
72.6% complete
Units sold
17 of 26

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
8
Unit mix
24 res ยท 2 comm
Architect
Allied Associates

Buyer community

Connect with other buyers and owners of JAI SHREERAM PRASANNA CHSL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching JAI SHREERAM PRASANNA CHSL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.