Under construction

SIDDHI VINAYAK

by SHREE GANESH ENTERPRISES

CTS NO 371 PART 372 PART 373 PART, Borivali, 400064

High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 9.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
MaladMid-income

Retail-and-BPO hub with dense mid-income housing on both sides.

Growth drivers:
Mindspace offices, Link Road retail, Metro 2A.
Who buys here:
Mid-income families, first-time buyers.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800012209
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026
Construction
9.1% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2017
Floors
24

Buyer community

Connect with other buyers and owners of SIDDHI VINAYAK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SIDDHI VINAYAK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.