Under construction

GALAXY PINNACLE

by MR REALTORS

375 TO 379, Andheri, 400054

Mar 2021
Possession
45.5%
Built
2
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Sept 2019, now proposed Mar 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 45.5%.
Vile Parle East / AirportUpper-mid

Institutional belt (colleges, airport) with steady society redevelopment.

Growth drivers:
Airport economy, Metro 3, education cluster.
Who buys here:
Airline/airport professionals, Parle loyalists.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800012634
Status
Ongoing
Stage
Certificate Signed
Possession
March 2021originally September 2019
Construction
45.5% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Sept 2017
Floors
7

Buyer community

Connect with other buyers and owners of GALAXY PINNACLE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GALAXY PINNACLE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.