Under construction

Avant Heritage II-Basement plus stilt plus 3 Podium plus 20 Upper Habitable Floors

by Aishwarya Avant Builders LLP

CTS No. 156 D part, Andheri, 400060

High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2021, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 80%.

Official RERA facts

Registration
P51800015537
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally June 2021
Construction
80% complete
Units sold
0 of 0

RERA complaint record5 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains70%
Landscaping & Tree Planting50%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements40%
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Space50%

Building & registration

RERA registered
Mar 2018
Floors
26

Buyer community

Connect with other buyers and owners of Avant Heritage II-Basement plus stilt plus 3 Podium plus 20 Upper Habitable Floors โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Avant Heritage II-Basement plus stilt plus 3 Podium plus 20 Upper Habitable Floors. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.