AVD RESIDENCIA
CTS NO F 526 OF VILLAGE BANDRA, Andheri, 400050
Oct 2024
Possession
100%
Built
0
Complaints
0
Units
Caution
- Possession delayed ~2 yrs. Originally promised Mar 2023, now proposed Oct 2024 per the RERA filing.
Official RERA facts
- Registration
- P51800017156
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2024originally March 2023
- Construction
- 100% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 20 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains75%
Landscaping & Tree Planting50%
Water conservation /Rain water harvesting75%
Energy managemcntnot started
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station75%
SOCIETY OFFICEdone
Building & registration
- RERA registered
- Jul 2018
- Floors
- 11
Buyer community
Connect with other buyers and owners of AVD RESIDENCIA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AVD RESIDENCIA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.