PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

LODHA ETERNIS SERENA C

by LODHA DEVELOPERS LIMITED

CTS No.67, 67/1, 74, 75, 75/1 TO 14, 78, 80 PART ONE ONLY OF VILLAGE MULGAON, Andheri, 400093

High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 83.6%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P51800020147
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
83.6% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains80%
Landscaping & Tree Planting70%
Street Lighting80%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Spacenot started
Open Parking80%
Closing Parking70%
Closed Parkings80%

Building & registration

RERA registered
Mar 2019
Floors
13

Buyer community

Connect with other buyers and owners of LODHA ETERNIS SERENA C โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LODHA ETERNIS SERENA C. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.