PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

CHEMBUR SHRAVAN

by JOHN DENNIS CONSTRUCTIONS PVT. LTD.

CST NO 56 PT, CHEMBUR WEST, 400071

Dec 2026
Possession
42.6%
Built
2
Complaints
78
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Sept 2024, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 42.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800022435
Status
New
Stage
Certificate Signed
Possession
December 2026originally September 2024
Construction
42.6% complete
Units sold
54 of 78

RERA complaint record2 records

  • ComplaintCC1260151119 Mar 2026
    HASID HAMID MANSURI vs JOHN DENNIS CONSTRUCTIONS PVT. LTD.
  • ComplaintCC0060000002096397 Jan 2022
    prashant prakash shelar vs JOHN DENNIS CONSTRUCTION PVT LTD ( DENNIS FERNANDES )
    Order of Prashant shelar.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2019
Floors
17
Unit mix
78 res ยท 0 comm
Architect
KEN ASSIST

Buyer community

Connect with other buyers and owners of CHEMBUR SHRAVAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching CHEMBUR SHRAVAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.