Under construction

MONTANA PHASE - 4

by LOHITKA PROPERTIES LLP

OUT OF CTS 514, 531P, 531/1 TO 14, 532A-P AND 534P, Kurla, 400080

Dec 2026
Possession
71.8%
Built
2
Complaints
375
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
MulundUpper-mid

Leafy eastern-suburb favourite with big redevelopment supply.

Growth drivers:
Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
Who buys here:
Eastern-suburb families upgrading within the area.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800026393
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
71.8% complete
Units sold
364 of 375

RERA complaint record2 records

  • ComplaintCC0060000005913651 Aug 2024
    Lohitka LLP vs Ramesh B Kawle
    83o.pdf on MahaRERA
  • Misc. applicationCC0060000005913651 Aug 2024
    Lohitka LLP vs Ramesh B Kawle

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station25%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2020
Floors
49
Unit mix
375 res · 0 comm
Architect
Sandeep Shirke And Associates

Buyer community

Connect with other buyers and owners of MONTANA PHASE - 4 — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching MONTANA PHASE - 4. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.