Nasar Enclave Sale Building A and B Wing

by M/s. Nasar Associates

195 part, 208 part, 812 and 813, Andheri, 400058

Jun 2026
Possession
77.9%
Built
0
Complaints
174
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 77.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800028733
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
77.9% complete
Units sold
63 of 174

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space90%
Open Parkingnot started

Building & registration

RERA registered
Mar 2021
Floors
18
Unit mix
162 res · 12 comm
Architect
AASHISH SOLANKI

Buyer community

Connect with other buyers and owners of Nasar Enclave Sale Building A and B Wing — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Nasar Enclave Sale Building A and B Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.