Under construction

Ornata - Amber

by SPENTA ENCLAVE PRIVATE LIMITED

343 Part, Kurla, 400071

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2024, now proposed Dec 2029 per the RERA filing.
Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800028964
Status
New
Stage
Certificate Signed
Possession
December 2029originally December 2024
Construction
5.5% complete
Units sold
22 of 202

RERA complaint record1 record

  • ComplaintCC00600000029236014 Sept 2022
    Nikhil Tukaram Kerkar vs Spenta Enclave Private LTD

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Apr 2021
Floors
32
Unit mix
202 res ยท 0 comm
Architect
Rajendra Ulhas Pagnis

Buyer community

Connect with other buyers and owners of Ornata - Amber โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Ornata - Amber. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.