PropPin
All RERA projects
🏗️
Under construction

MARIGOLD AANGAN

by MARIGOLD CONSTRUCTIONS

795 795 1TO9 796 796 1TO9, Kurla, 400080

Jun 2026
Possession
81.8%
Built
1
Complaints
76
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2024, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
MulundUpper-mid

Leafy eastern-suburb favourite with big redevelopment supply.

Growth drivers:
Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
Who buys here:
Eastern-suburb families upgrading within the area.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800029006
Status
New
Stage
Certificate Signed
Possession
June 2026originally March 2024
Construction
81.8% complete
Units sold
40 of 76

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposal80%
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Apr 2021
Floors
20
Unit mix
67 res · 9 comm
Architect
RP ASUNDARIA

Buyer community

Connect with other buyers and owners of MARIGOLD AANGAN — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching MARIGOLD AANGAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.