Under construction

PLATINUM 53 WEST

by PLATINUMCORP DEVELOPERS LLP

CTS NO 195 PART SURVEY NO 106 A, ANDHERI WEST, 400053

Dec 2028
Possession
90.9%
Built
0
Complaints
131
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2025, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51800031057
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2025
Construction
90.9% complete
Units sold
53 of 131

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Oct 2021
Floors
19
Unit mix
116 res ยท 15 comm
Architect
SPACE MOULDERS

Buyer community

Connect with other buyers and owners of PLATINUM 53 WEST โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PLATINUM 53 WEST. Real notes from real buyers beat any brochure.

Start a discussion