PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

NIRVAANA PEARL

by Nirvaana Lifespace LLP

826 Part, Kurla, 400007

High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 41%.

Official RERA facts

Registration
P51800032083
Status
New
Stage
Certificate Signed
Possession
June 2026originally June 2025
Construction
41% complete
Units sold
40 of 107

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2021
Floors
16
Unit mix
95 res ยท 12 comm
Architect
Ritesh Thakur

Buyer community

Connect with other buyers and owners of NIRVAANA PEARL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIRVAANA PEARL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.