Under construction

THE SANCTUARY - TOWER 2

by Runwal Construction Private Limited

544 and 544/1, Kurla, 400080

Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51800032538
Status
New
Stage
Certificate Signed
Possession
March 2027
Construction
58.3% complete
Units sold
185 of 264

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains15%
Landscaping & Tree Planting5%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting10%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station20%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2022
Floors
52
Unit mix
264 res ยท 0 comm

Buyer community

Connect with other buyers and owners of THE SANCTUARY - TOWER 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE SANCTUARY - TOWER 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.