Under construction

Building no 3 Wing C Aquila

by S D CORPORATION PRIVATE LIMITED

840 A1 Part, Borivali, 400101

High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 38.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800032647
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
38.9% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC1250458022 Dec 2025
    ANIL KUMAR AGARWAL vs Aman Yadav

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2022
Floors
46

Buyer community

Connect with other buyers and owners of Building no 3 Wing C Aquila โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Building no 3 Wing C Aquila. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.