Under construction

Sidhivinayak Flora

by SIDHIVINAYAK CONSTRUCTIONS

CTS No 454/19 and 454/20, Kurla, 400071

Caution
  • Possession delayed ~2 yrs. Originally promised Aug 2024, now proposed Dec 2026 per the RERA filing.
Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800033003
Status
New
Stage
Certificate Signed
Possession
December 2026originally August 2024
Construction
88.7% complete
Units sold
25 of 56

RERA complaint record1 record

  • ComplaintCC126026296 May 2026
    Veena Dewan vs SIDHIVINAYAK CONSTRUCTIONS

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Landscaping & Tree Planting50%
Street Lightingnot started
Water conservation /Rain water harvesting95%
Energy managemcntnot started
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2022
Floors
12
Unit mix
56 res ยท 0 comm
Architect
Ashish Atmaram Pachupate

Buyer community

Connect with other buyers and owners of Sidhivinayak Flora โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sidhivinayak Flora. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.