Under construction

SWAMINARAYAN DHAM

MahaRERA P51800033497High risk

by ARA BUILDERS PRIVATE LIMITED

837, Andheri, 400072

Official record
Dec 2026
Possession
77.9%
Built
0
Complaints
154
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Chandivali / SakinakaMid-income

Powai's value flank โ€” newer towers between industrial pockets.

Growth drivers:
Powai spillover, Metro 1, airport belt jobs.
Who buys here:
Buyers priced out of Powai proper.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800033497
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
77.9% complete
Units sold
142 of 154

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA17022619879Revised to December 2026

    Subject: Submission of Technical Reasons for Delay in Completion of the Project known as "SWAMINARAYAN DHAM" bearing Maha RERA Reg. No. P51800033497. Respected Sir/Madam, 1 Manoj R. Vishwasrao, Director of Ms/. ARA Builders Private Limited, is the promoter of the real estate project known as "Swaminarayan Dham", bearing MahaRERA Registration No. P51800033497. The project, which was initially scheduled for completion by 31/12/2025. The primary reason for the delay is the implementation of significant design changes during the course of development. These changes were undertaken to enhance the overall structural integrity, functionality, and quality of the project, and to align the development with updated regulatory requirements and improved planning standards. We assure the Authority that the delay was neither intentional nor due to negligence. The modifications were carried out to ensure improved safety, compliance, and long-term value of the project. We remain fully committed to completing the project at the earliest possible date and are taking all necessary measures to expedite the remaining work.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2022
Floors
15
Unit mix
141 res ยท 13 comm
Architect
ASHISH SOLANKI
Plot / CTS / survey no.
837
Planning authority
Others
Approved layout land
4,497.3 sq.m
Land for this registration
4,497.3 sq.m
Recreational open space
665.7 sq.m
Permissible built-up area
5,163 sq.m
Registered office
RAJVEER ROYALS
Plot boundaries
North
CTS NO 833 AND 834
South
CTS NO 839
East
CTS NO 834 AND 835
West
ANDHERI KURLA ROAD
Parking

Buyer community

Connect with other buyers and owners of SWAMINARAYAN DHAM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SWAMINARAYAN DHAM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.