PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Goregaon Manorath CHS LTD

by K Anand Infra

Plot No 85 CTS No 436 436/1 and 2, Borivali, 400063

Dec 2027
Possession
47.7%
Built
1
Complaints
40
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Mar 2026, now proposed Dec 2027 per the RERA filing.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800033980
Status
New
Stage
Certificate Signed
Possession
December 2027originally March 2026
Construction
47.7% complete
Units sold
5 of 40

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Solid Waste Management And Disposal60%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2022
Floors
16
Unit mix
40 res ยท 0 comm
Architect
plan axis architects

Buyer community

Connect with other buyers and owners of Goregaon Manorath CHS LTD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Goregaon Manorath CHS LTD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.