PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ODC 1

by NVN Buildcon LLP

C.T.S. No.71, 71/1 to 8, Goregaon West, 400104

Jul 2026
Possession
81.8%
Built
0
Complaints
86
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 81.8%.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800046544
Status
New
Stage
Certificate Signed
Possession
July 2026originally December 2024
Construction
81.8% complete
Units sold
63 of 86

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2022
Floors
21
Unit mix
86 res ยท 0 comm

Buyer community

Connect with other buyers and owners of ODC 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.