Under construction

33 WEST

by SILVER LIFESPACES PRIVATE LIMITED

CTS NO F/362, Mumbai, 400052

Dec 2026
Possession
47.6%
Built
0
Complaints
10
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 47.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800047213
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
47.6% complete
Units sold
4 of 10

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Oct 2022
Floors
20
Unit mix
9 res ยท 1 comm
Architect
Aashish solanki

Buyer community

Connect with other buyers and owners of 33 WEST โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 33 WEST. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.