PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MDM MAESTRO

by MDM REALTY LLP

833(pt), Andheri, 400053

Dec 2026
Possession
52.7%
Built
0
Complaints
46
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800048676
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
52.7% complete
Units sold
13 of 46

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2023
Floors
11
Unit mix
46 res ยท 0 comm
Architect
MS SANJAY B SHAH

Buyer community

Connect with other buyers and owners of MDM MAESTRO โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MDM MAESTRO. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.