All RERA projects
๐๏ธ
Dec 2026
Possession
45%
Built
1
Complaints
0
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 45%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Parel / Dadar EastPremium
Mill-land towers around Maharashtra's busiest rail junction.
- Growth drivers:
- Hospital cluster jobs, central location, mill plot launches.
- Who buys here:
- South-Bombay workers wanting new construction.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51800048773
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 45% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00600000048029628 Apr 2024Madhusudan Chintaman Pitkar vs M/S Chetna EnterprisesOrder of Madhusudan Pitkar (3).pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Jan 2023
- Floors
- 23
Buyer community
Connect with other buyers and owners of The Autograph โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching The Autograph. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.