Under construction

Hill Star

by Right Channel Buildcon LLP

446, Borivali, 400097

Jun 2027
Possession
75%
Built
0
Complaints
20
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Kharghar / PanvelValue

The airport-bet frontier โ€” golf course, hills and heavy new supply.

Growth drivers:
Navi Mumbai International Airport, MTHL access, NAINA planning zone.
Who buys here:
First-time buyers and investors betting on the airport economy.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800048810
Status
New
Stage
Certificate Signed
Possession
June 2027originally December 2024
Construction
75% complete
Units sold
18 of 20

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2023
Floors
16
Unit mix
20 res ยท 0 comm
Architect
Planwell Architects

Buyer community

Connect with other buyers and owners of Hill Star โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Hill Star. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.