Under construction

ASCEND TOWER

by M. MAMTORA ASSOCIATES

981, Borivali, 400064

Dec 2027
Possession
60.2%
Built
0
Complaints
183
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2026, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
MaladMid-income

Retail-and-BPO hub with dense mid-income housing on both sides.

Growth drivers:
Mindspace offices, Link Road retail, Metro 2A.
Who buys here:
Mid-income families, first-time buyers.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800049273
Status
New
Stage
Certificate Signed
Possession
December 2027originally June 2026
Construction
60.2% complete
Units sold
38 of 183

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains65%
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station25%

Building & registration

RERA registered
Feb 2023
Floors
22
Unit mix
183 res ยท 0 comm
Architect
SANJAY B SHAH

Buyer community

Connect with other buyers and owners of ASCEND TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ASCEND TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.