Under construction

Supreme AloraMahaRERA P51800049923

by Supreme Sky Ventures LLP

670, Khar, 400052

Apr 2026
Possession
73.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 73.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2026 per the RERA filing.

Official RERA facts

Registration
P51800049923
Status
New
Stage
Certificate Signed
Possession
April 2026
Construction
73.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains15%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting10%
Fire protection and fire safety requirements40%
Electrical meter room, sub-station, receiving station50%
Open Parkingnot started

Building & registration

RERA registered
Mar 2023
Floors
15

Buyer community

Connect with other buyers and owners of Supreme Alora โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Supreme Alora. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.