Under construction

Arham Aryan

by Trinity Builders

1057, 1057/ 1 to 5, Kurla, 400071

Dec 2026
Possession
43.2%
Built
0
Complaints
29
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800050811
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
43.2% complete
Units sold
10 of 29

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2023
Floors
10
Unit mix
29 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Arham Aryan โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Arham Aryan. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.