REDEVELOPMENT OF PEARL PALACE

by PRANAV CONSTRUCTIONS LIMITED

206 ,207, Andheri, 400054

Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.

Official RERA facts

Registration
P51800051212
Status
New
Stage
Certificate Signed
Possession
September 2027
Construction
72.7% complete
Units sold
9 of 26

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposal25%
Water conservation /Rain water harvesting25%
Fire protection and fire safety requirements40%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jun 2023
Floors
16
Unit mix
23 res ยท 3 comm
Architect
RASIK P HINGOOAND ASSOCIATES

Buyer community

Connect with other buyers and owners of REDEVELOPMENT OF PEARL PALACE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching REDEVELOPMENT OF PEARL PALACE. Real notes from real buyers beat any brochure.

Start a discussion