PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Kaveri TowerMahaRERA P51800051955

by Gnanesh Virendra Lakhia

285, 285/1 & 2, 285/4 TO 6 & 247(pt), Andheri West, 400058

Dec 2025
Possession
77.7%
Built
0
Complaints
41
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 77.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P51800051955
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
77.7% complete
Units sold
17 of 41

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jul 2023
Floors
14
Unit mix
34 res ยท 7 comm
Architect
SAUMIL ASHWIN JHAVERI M/s H.M.Jhaveri & Sons. ASHWIN JHAVERI

Buyer community

Connect with other buyers and owners of Kaveri Tower โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kaveri Tower. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.