Under construction

Sidhivinayak Orchid

by Sidhivinayak Developers

186 Part, Kurla, 400075

High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 40.9%.
  • Promised amenities not started. Gymnasium, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800052348
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
40.9% complete
Units sold
0 of 1

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Fitness Centernot started

Building & registration

RERA registered
Aug 2023
Floors
12
Architect
Space Design

Buyer community

Connect with other buyers and owners of Sidhivinayak Orchid โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sidhivinayak Orchid. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.