Under construction

Piramal Aranya - Wing A

by Glider Buildcon Realtors Private Limited

Cadastral Survey No. 593 -part- of Mazgaon Division, Mumbai City, 400010

High risk
  • 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2024 per the RERA filing.

Official RERA facts

Registration
P51900003324
Status
Ongoing
Stage
Certificate Signed
Possession
December 2024
Construction
90.9% complete
Units sold
148 of 229

RERA complaint record11 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
67
Unit mix
229 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Piramal Aranya - Wing A โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Piramal Aranya - Wing A. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.