Under construction

Krishvi ApartmentsMahaRERA P51900004145

by M/s Shagun Construction

829, 830, -, 400004

Aug 2025
Possession
90.9%
Built
0
Complaints
94
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2018, now proposed Aug 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2025) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2025 per the RERA filing.
Girgaon / Grant RoadPremium

Heritage chawl-and-wadi belt in cluster redevelopment mode.

Growth drivers:
Cluster redevelopment policy, Metro 3, Coastal Road.
Who buys here:
South-Bombay natives staying local in new towers.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51900004145
Status
Ongoing
Stage
Certificate Signed
Possession
August 2025originally December 2018
Construction
90.9% complete
Units sold
44 of 94

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
24
Unit mix
82 res ยท 12 comm
Architect
Aakar Architects and Consultants

Buyer community

Connect with other buyers and owners of Krishvi Apartments โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Krishvi Apartments. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.