Dec 2026
Possession
70.5%
Built
4
Complaints
130
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51900004931
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2021
- Construction
- 70.5% complete
- Units sold
- 35 of 130
RERA complaint record4 records
- ComplaintCC1240013217 Sept 2024Pratima Kashyap Shende vs M/s. virtue EnterprisesCC006000000591500APPLRV2 VIRTUE ENTERPRISE.pdf on MahaRERA
- Misc. applicationCC00600000059150010 Aug 2024Kashyap Manohar Shende vs M/s Virtue Enterprise
- ComplaintCC00600000059150010 Aug 2024Kashyap Manohar Shende vs M/s Virtue EnterpriseCC006000000591500APPLRV2 VIRTUE ENTERPRISE.pdf on MahaRERA
- ComplaintCC00600000025148415 Jun 2022KASHYAP MANOHAR SHENDE vs VIRTUE ENTERPRISEFinal Order 251484.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drainsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station90%
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 21
- Unit mix
- 126 res ยท 4 comm
Buyer community
Connect with other buyers and owners of Promesa West End โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Promesa West End. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.