VARDHMAN FLORA PHASE I

by VARDHMAN DEVELOPERS LTD

1/750, 1A/750, 751, Mumbai City, 400033

Dec 2026
Possession
67.5%
Built
3
Complaints
113
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51900008829
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
67.5% complete
Units sold
73 of 113

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water20%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting20%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
57
Unit mix
113 res ยท 0 comm

Buyer community

Connect with other buyers and owners of VARDHMAN FLORA PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VARDHMAN FLORA PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.