PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

BHIVAWANI CHAWL

MahaRERA P51900011643High risk

by MS RADHAKRISHNA DEVELOPER

CS NO 377 PAREL VILLAGE ROAD PAREL 400012, Mumbai City, 400012

Official record
Dec 2026
Possession
81.4%
Built
0
Complaints
47
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51900011643
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
81.4% complete
Units sold
15 of 47

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EXT51900017901Revised to December 2024

    In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

  • EXT51900027216Revised to December 2025

    We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31/12/2025 to complete the project and fulfil all regulatory requirements.

  • EA09122518585Revised to December 2026

    The project has successfully obtained Part Occupancy Certificate (OC) for Basement, Ground Floor, 1st to 17th Floors, and 18th Upper Floor (Except Flat No. 45). All completed units have been constructed as per the sanctioned plans, and statutory compliances for these portions have been duly fulfilled. However, OC for Flat No. 45 on the 18thUpper Floor is still pending due to obtain the NOC from Archaeological survey of India and thereafter to obtain final OC after which project will be fully complete

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drains75%
Landscaping & Tree Plantingnot started
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving station25%

Building & registration

RERA registered
Aug 2017
Floors
20
Unit mix
45 res ยท 2 comm
Architect
P N BHOBE AND ASSOCIATES
Plot / CTS / survey no.
CS NO 377 PAREL VILLAGE ROAD PAREL 400012
Planning authority
Municipal Corporation of Greater Mumbai
Approved layout land
234.95 sq.m
Land for this registration
234.95 sq.m
Permissible built-up area
2,087.24 sq.m
Registered office
RAM BHUWAN RESIDENCY
Plot boundaries
North
C NO 2 324 PAREL SEWREE DIVISION
South
BY PAREL VILLAGE ROAD
East
C NO 376 OF PAREL SEWREE DIV
West
BY PUBLIC ROAD
Parking
12 four-wheeler

Buyer community

Connect with other buyers and owners of BHIVAWANI CHAWL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BHIVAWANI CHAWL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.