Under construction

1 OSR

by Shagun Builders

FP no 81, Ward GNorth, 400016

Mar 2023
Possession
90.9%
Built
2
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 90.9%.

Official RERA facts

Registration
P51900014754
Status
New
Stage
Certificate Signed
Possession
March 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains10%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station60%

Building & registration

RERA registered
Jan 2018
Floors
23

Buyer community

Connect with other buyers and owners of 1 OSR โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 1 OSR. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.