PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Samruddhi Heights

by HIGH RISE REALTY PRIVATE LIMITED

Plot no 125 C S no.326/10, Mumbai City, 400019

Mar 2021
Possession
76%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 76%.

Official RERA facts

Registration
P51900017743
Status
New
Stage
Certificate Signed
Possession
March 2021
Construction
76% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drains85%
Water conservation /Rain water harvesting85%
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station85%
Staircase and main passage lobbies compound RCC underground water tank75%
SIDE MARGIN PAVEMENT35%
RCC overhead water tankdone
Pumps Lifts and electrical fittings in staircase entrance lobby compound and terrace85%

Building & registration

RERA registered
Sept 2018
Floors
17

Buyer community

Connect with other buyers and owners of Samruddhi Heights โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Samruddhi Heights. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.