Under construction

NCP Commercial Tower - Supremus

by LODHA DEVELOPERS LIMITED

Block C, WTT, C.S. No.8 Pt. Salt Pan Division, Ward FNorth, 400022

High risk
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.

Official RERA facts

Registration
P51900021485
Status
New
Stage
Certificate Signed
Possession
March 2024
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains25%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements10%
Electrical meter room, sub-station, receiving station20%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jul 2019
Floors
17

Buyer community

Connect with other buyers and owners of NCP Commercial Tower - Supremus โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NCP Commercial Tower - Supremus. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.