Caution
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 81.8%.

Official RERA facts

Registration
P51900022549
Status
New
Stage
Certificate Signed
Possession
December 2019
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
PLAZA AREA AS IDENTIFIED IN THE ATTACHED MAPdone
2 SERVICE LIFTS LOCATED IN THE BUILDINGdone
4 BASEMENT PARKING LIFTSdone
MEP BUILDING HOUSING THE ELECTRIC EQUIPMENT DG SETS AND OTHER EQUIPMENT RELATED TO THE BUILDINGdone

Building & registration

RERA registered
Oct 2019
Floors
26

Buyer community

Connect with other buyers and owners of NCP Commercial Tower 1 - up to 22nd Floor โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NCP Commercial Tower 1 - up to 22nd Floor. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.