THE METROPOLEMahaRERA P51900026208
F.P NO 36 AND 37 OF TPS II, GHATKOPAR, 400086
Mar 2024
Possession
81.4%
Built
14
Complaints
147
Units
High risk
- 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 81.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.
Ghatkopar / VikhroliUpper-mid
Metro-1 anchor with Godrej's Vikhroli land bank next door.
- Growth drivers:
- Metro 1 interchange, Eastern Express Highway, corporate campuses.
- Who buys here:
- Families wanting east-side connectivity to BKC/Fort.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51900026208
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2024
- Construction
- 81.4% complete
- Units sold
- 44 of 147
RERA complaint record14 records
- ComplaintCC00600000048015921 Apr 2024MILAN RAJNIKANT TANNA vs M/S. RAVESHIA REALTORS
- ComplaintCC00600000048013921 Apr 2024MILAN RAJNIKANT TANNA vs M/S. RAVESHIA REALTORS
- ComplaintCC00600000048014021 Apr 2024MILAN RAJNIKANT TANNA vs M/S. RAVESHIA REALTORS
- ComplaintCC00600000048015221 Apr 2024MILAN RAJNIKANT TANNA vs M/S. RAVESHIA REALTORS
- ComplaintCC00600000048015421 Apr 2024MILAN RAJNIKANT TANNA vs M/S. RAVESHIA REALTORS
- ComplaintCC00600000048015521 Apr 2024MILAN RAJNIKANT TANNA vs M/S. RAVESHIA REALTORS
- ComplaintCC00600000048015721 Apr 2024MILAN RAJNIKANT TANNA vs M/S. RAVESHIA REALTORS
- ComplaintCC00600000042905426 Feb 2024Raveshia Realtors vs Mr. Milan Rajnikant Tanna
- ComplaintCC00600000042935026 Feb 2024Raveshia Realtors vs Mr. Milan Rajnikant Tanna
- ComplaintCC00600000042935726 Feb 2024Raveshia Realtors vs Mr. Milan Rajnikant Tanna
- ComplaintCC00600000042935926 Feb 2024Raveshia Realtors vs Mr. Milan Rajnikant Tanna
- ComplaintCC00600000042936026 Feb 2024Raveshia Realtors vs Mr. Milan Rajnikant Tanna
- ComplaintCC00600000042936226 Feb 2024Raveshia Realtors vs Mr. Milan Rajnikant Tanna
- ComplaintCC00600000042936326 Feb 2024Raveshia Realtors vs Mr. Milan Rajnikant Tanna
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains60%
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station80%
Building & registration
- RERA registered
- Aug 2020
- Floors
- 17
- Unit mix
- 0 res ยท 147 comm
- Architect
- YMS Consultants Limited
Buyer community
Connect with other buyers and owners of THE METROPOLE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching THE METROPOLE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.