PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

DOSTI EASTERN BAY - PHASE 3

by DOSTI REALTY LTD

CS 2A-116 SALT PAN DIVISION, Mumbai City, 400037

Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51900032067
Status
New
Stage
Certificate Signed
Possession
September 2027
Construction
97.3% complete
Units sold
367 of 377

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Dec 2021
Floors
49
Unit mix
377 res ยท 0 comm
Architect
RAMNANI & ASSOCIATES

Buyer community

Connect with other buyers and owners of DOSTI EASTERN BAY - PHASE 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DOSTI EASTERN BAY - PHASE 3. Real notes from real buyers beat any brochure.

Start a discussion