Under construction
Amaris ParkMahaRERA P51900050469
by TRIDHAATU JEHANGIR MANSION DEVELOPERS LLP
734/10, MATUNGA, 400019
Apr 2026
Possession
99.5%
Built
0
Complaints
19
Units
Caution
- Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 99.5%.
Official RERA facts
- Registration
- P51900050469
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2026
- Construction
- 99.5% complete
- Units sold
- 2 of 19
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting90%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Apr 2023
- Floors
- 18
- Unit mix
- 19 res ยท 0 comm
- Architect
- GA DESIGN
Buyer community
Connect with other buyers and owners of Amaris Park โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Amaris Park. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.