Under construction

KANKESHWAR VRINDAVAN

by KANKESHWARA BUILDCON PRIVATE LIMITED

SURVEY NO 51 HISSA NO 2, ALIBAG, 402201

Mar 2023
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2020, now proposed Mar 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.

Official RERA facts

Registration
P52000000991
Status
Ongoing
Stage
Certificate Signed
Possession
March 2023originally March 2020
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2017
Floors
5

Buyer community

Connect with other buyers and owners of KANKESHWAR VRINDAVAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KANKESHWAR VRINDAVAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.