Indraprashth
92/2A, 92/2B, 93A/4+5, Dasturi Naka, 402301
Dec 2026
Possession
40.5%
Built
0
Complaints
58
Units
High risk
- Possession delayed ~8 yrs. Originally promised Jun 2019, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 40.5%.
Official RERA facts
- Registration
- P52000005562
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2019
- Construction
- 40.5% complete
- Units sold
- 9 of 58
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Treatment And Disposal Of Sewage And Sullage Water90%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station95%
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 8
- Unit mix
- 58 res ยท 0 comm
Buyer community
Connect with other buyers and owners of Indraprashth โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Indraprashth. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.