Under construction

NANO CITY

by NIRMAN REALTORS AND DEVELOPERS LTD

Survey No. 44 1B 3B , Karjat, 410201

Dec 2029
Possession
29.7%
Built
5
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2025, now proposed Dec 2029 per the RERA filing.

Official RERA facts

Registration
P52000006161
Status
Ongoing
Stage
Certificate Signed
Possession
December 2029originally December 2025
Construction
29.7% complete
Units sold
0 of 0

RERA complaint record5 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths25%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
3
Architect
Rushika Sawant

Buyer community

Connect with other buyers and owners of NANO CITY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NANO CITY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.