Under construction

Garva Residency-C3

by Garva Developers Pvt Ltd

25/B, Warse, 402116

Dec 2017
Possession
70%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 70%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2017 per the RERA filing.

Official RERA facts

Registration
P52000006946
Status
Ongoing
Stage
Certificate Signed
Possession
December 2017
Construction
70% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply85%
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Landscaping & Tree Planting10%
Street Lighting90%
Community Buildingsnot started
Electrical meter room, sub-station, receiving station50%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of Garva Residency-C3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Garva Residency-C3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.