MORYA HOME TOWN

MahaRERA P52000007069High risk

by MORYA INFRACONSTRUCT PRIVATE LIMITED

180/1, 181/2, 182, NAGOTHANE, 402106

Official record
Dec 2027
Possession
72.2%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
MORYA INFRACONSTRUCT PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000007069
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2024
Construction
72.2% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)15%
Storm Water Drains20%
Landscaping & Tree Planting35%
Street Lighting20%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station7.5%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of MORYA HOME TOWN — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching MORYA HOME TOWN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.